Compare & price
HomeGuidesLe datacenter maison

Home data center guide: advice, opinions and trends

Building a server room on your own premises is feasible, often cheaper than expected to buy, and almost always dearer than expected to run. This guide says both.

Estimate my cost →

The essentials, if you read nothing else #

Build on your own site, or rent from a provider: the table that settles it #

We repeat below that under five racks colocation deserves to be costed. We may as well put the criteria side by side straight away.

The criterionOn your siteWith a provider
What you pay up front€40,000 to €110,000 at onceNothing, or setup fees
What you pay every year€45,000 to €70,000, electricity includedA rent, power included or rebilled
Who answers at nightYou, or nobodyAn on-call team, contractually
Who carries the liabilityYou, fire and access includedThe provider, within the contract
If you grow by halfBuilding works, perhaps a moveOne more rack, within weeks
If you relocatePart of the investment stays on the wallYou terminate at the end of the term
What you keepFull control and physical proximityTime, and someone accountable

⚠️ There is no general right answer, there is a right answer for your acceptable downtime. If your business can absorb a day of outage, a room of your own may well be enough and will cost you less in constraints. If it cannot absorb two hours, you are buying on-call cover you will not actually have.

What this guide calls a home data center #

A server room installed in your own premises: between one and about thirty racks, in a building that was never designed for it. That is the case of a small company, a local authority, a practice, an industrial site keeping its data in house.

It is not a data center in the professional sense: no site redundancy, no on-call team, no certification. That is not an insult — many companies need nothing more. The mistake would be to believe you build one by buying the components of the other.

Everything below is costed by our sizing tool, which applies the French NF C 15-100 method to the assumptions you enter. The figures quoted here are orders of magnitude: some are market references, others are estimates, and the tool says which.

Our advice before you buy anything #

Three questions decide the project, and none of them is solved with money. Ask them before you request the first quote.

⚠️ And one piece of advice that costs almost nothing: drilling through a fire-rated wall means sealing it again immediately, back to its rating, with a certified system. Not when the tenant leaves: as soon as the cables are pulled. While the hole is open, the building's fire compartmentation is breached, and that is the path smoke takes.

The real budget: what you buy once, and what comes back every year #

Here is a four-rack room at 3 kW, under lease, with overhead cable tray. Figures are low and high brackets, excluding tax.

Line itemTo buyPrice status
4 empty 42 U racks€3,200 – 10,000market reference
Power strips, 2 per rack€720 – 2,400estimated
Protected feeds from the board€1,600 – 6,000estimated
Overhead cable tray, 15 m€225 – 600estimated
Copper and optical patching€2,600 – 9,600estimated
Precision cooling€14,400 – 30,000market reference
UPS and batteries€9,480 – 12,480market reference
Fire detection and suppression€5,000 – 20,000market reference
Access control and video€3,000 – 10,000market reference
Mesh earthing, blanking panels, entries€1,150 – 4,280estimated
Total to buy€41,600 – 111,300
And every year€45,200 – 69,300/yrelectricity and maintenance

Read the last line twice. In under two years, running the room will have cost more than everything bought for it. A 12 kW IT room on comfort air conditioning runs at an energy ratio of 2.0 to 2.5: it can therefore draw up to 28 kW at the meter. ⚠️ That is an upper bound: cooling does not run at full load all year, and a unit sized for a heatwave draws less in February. Keep the order of magnitude, not the decimal.

That is the figure missing from almost every comparison, and it is the one that decides.

The five questions a managing director asks, and that the engineering does not answer #

This guide was first written from the point of view of whoever installs the room. An outside review reminded us that this is not the point of view of whoever decides. Here is what was missing.

Our opinion on the line items everyone forgets #

In the budget above, the four bold lines — cooling, UPS, fire, security — weigh more than all the rest combined. They are not options: they are the items that never appear on a list written from memory.

Maximum power per rack is not chosen, it is imposed #

A rack's capacity follows the weakest-link rule: the cooling available, the cable feeding it, or your electricity contract. Delivering 22 kW to a rack achieves nothing if your cooling only removes 5: the rack will overheat within minutes.

This is the costliest misunderstanding in small-company sizing, and here are the three ceilings in detail.

CeilingWhat it is worthWho sets it
Thermal5 kW open air · 10 kW contained aisles · 40 kW liquidyour cooling
Electrical16 A 1-ph ≈ 3.7 kVA · 32 A 1-ph ≈ 7.4 kVA · 16 A 3-ph ≈ 11.1 kVA · 32 A 3-ph ≈ 22.2 kVA. ⚠️ A strip is rated in kVA, heat is counted in kW: with the power factor of modern servers, 22.2 kVA yield only about 21 kW usable.your power strip
Contractualwhat your meter allows, across all usesthe network operator

⚠️ The trap: buying a 32 A three-phase strip and believing you can load 22 kW into the rack, when the real ceiling is 5 kW, that of comfort air conditioning. A power strip does not create cooling.

Our advice: cold aisle containment takes a rack from 5 to 10 kW, and therefore halves the number of racks needed. It is not weighed as a comfort, it is weighed against buying more racks.

Where the cables run: six cases, and only one to refuse #

Routing is not an installation detail. Do not overlook the route of the power cables: packed together or exposed to heat, they risk overheating. Your electrician will then have to install thicker — and considerably dearer — cables to meet the safety rules. Decide the route before costing the cables, or you pay twice.

SolutionIndicative priceOur opinion
Wire mesh tray, overhead€15 – 40/mThe default for a small company: fast, reversible, no building work
Perforated tray, overhead€30 – 70/mWhen loads must be carried or dust kept out
Trunking or skirting, surface mounted€5 – 20/mOne or two racks, no more: grouping crushes the factors
Raised floor€70 – 350/m²Dedicated room. Under lease: feasible, conditionally
Mixed, power and data separated€40 – 90/mWhat actually happens once the site grows
Cables on the floorRefuse it. Trodden on, torn out, impossible to rework

On a 20 m² room with a 15 m run, overhead costs about €225 and a raised floor at least €1,400 — a factor of six, and up to eighteen in data center class. A small company does not need a raised floor; it needs to be told why.

⚠️ Your power cables and your network cables must run on separate routes, or you invite interference and intermittent faults. Formally forbid your contractor from mixing them in the same tray — that is a line for the tender, not a clearance for you to check yourself.

For the record, and for your installer: 200 mm between an unscreened power cable and an unscreened data cable, 50 mm if a steel divider separates them, crossing at 90°. Optical fibre escapes those distances — but not crushing.

Our opinion on structured cabling: when it starts paying #

Structured cabling is not a luxury you treat yourself to as you grow. It is an investment that pays once a link repeats often enough — and below that, it costs more than it returns. Saying so is as useful as recommending it.

SizeWhat you needPre-terminated trunks (MPO)
1 to 2 racksDirect patching, wall box for the carrierNo. There is nothing to prefabricate
3 to 10 racksOne distributor in a dedicated rackUseful: removes on-site termination
11 to 30 racksMain distributor plus zone distributorsRecommended
Over 30 racksDistribution zones, redundant main distributorStructural: it becomes a lead-time question

Do not go into the detail of optical fibre standards: leave that choice to your project manager. Copying terms you do not master into a tender means being steered by the first contractor who walks in.

Two contractual clauses are enough, and they protect you better than borrowed vocabulary:

⚠️ “Cabling guaranteed 20 years by the manufacturer” — that warranty only exists if the installer is approved by them, which rules out improvised work from the start.

⚠️ “Test report for every link handed over before the final payment” — the only clause that guarantees what was installed was actually measured, link by link.

Finally, a rule no specification ever writes: your carrier's engineer must never cross the server room to reach their equipment. Otherwise every visit becomes an escorted access, and in practice an unescorted one.

What your measurement is really worth, and why your PUE has no second decimal #

Do not steer your room by its energy ratio: entry-level meters show up to 40 % error at low load. That is all you need to take away; what follows explains it for those interested in measurement.

A ratio is never more precise than the two meters that build it.

⚠️ That last line is the costliest trap in this whole guide. “5 % of full scale” is not “5 % of the reading”. On a 32 A strip it means ±1.6 A whatever the load. A rack drawing 13 A is therefore measured to ±12 %. A rack drawing 4 A, to ±40 %. The relative error explodes when the rack is lightly loaded — which is exactly the small-company case.

This is not a defect of the strip: most of its current sensors are low-cost components designed to protect the circuit against overload, not to measure. “Metered” does not mean “well measured”.

The direct consequence: with a main meter at 3 % and IT counted at 5 %, a displayed ratio of 1.6 actually sits between 1.5 and 1.7. Announcing 1.58 suggests a precision the instruments do not have, and the gap between 1.58 and 1.64 may be nothing but instrument noise. Our advice: never display more decimals than your meters support, and start by instrumenting the weakest link — a measurement chain is never better than its worst instrument.

Three subjects come up at every conference and on every blog in the sector. Here is what they are worth for a room of a few racks.

Our opinion, and it runs against our own tool: below five racks, building a room is rarely the right call. The fixed items — fire, security, UPS, cooling — do not divide, and they crush a small installation's budget. Colocation deserves at least to be costed alongside. Our tool computes both, and it does sometimes conclude you should not build.

What this guide does not cover #

It replaces neither an electrical contractor's study nor the verification of an approved body. Our tool's calculations apply the NF C 15-100 method to the assumptions you enter; they are provided for information and do not constitute a calculation note.

It also does not cover backup, disaster recovery, or application architecture. A perfect room protects nothing if the data exists in only one place.

Finally, several prices quoted here are estimates, with no verified source: they give an order of magnitude so nothing is forgotten, not a budget. Replace them with your own quotes.

FAQ #

What budget for a four-rack home data center?

Between €41,600 and €111,300 to buy, and €45,200 to €69,300 a year to run. In under two years, running it costs more than everything bought for it. The item that decides is the electricity consumed by cooling, not the price of the racks.

Can I build a server room if I am a tenant?

Yes. A lease does not forbid drilling: it requires written authorisation from the landlord, then reinstatement when you leave. That is not a refusal, it is an exit cost to provision from the first quote — and a reason to prefer, at equal price, what can be dismantled.

What maximum power per rack should I plan for?

The lowest of three ceilings: what your cooling removes (5 kW open air, 10 in contained aisles, 40 in liquid), what your power strip carries (3.7 to 22 kVA depending on rating), and what your meter allows across all uses. A power strip does not create cooling.

Do I need a raised floor?

Rarely, for a small company. On a 20 m² room, an overhead tray costs about €225 against at least €1,400 for a raised floor. And beyond 0.91 m of void, fire suppression under the floor generally becomes mandatory — an extra cost that never appears on the floor quote.

Can power and network share the same cable tray?

No. Allow 200 mm between an unscreened power cable and an unscreened data cable, 50 mm if a steel divider separates them, and cross them at 90° where they must cross. Optical fibre, immune to electromagnetic interference, escapes that distance — but not crushing.

Does my metered power strip give me a reliable PUE?

Not necessarily. Most current sensors in a power strip are low-cost components designed to protect the circuit against overload, not to measure. Their typical accuracy is 5 % of full scale: on a 32 A strip that is ±1.6 A whatever the load, or ±40 % on a rack drawing only 4 A.

How many decimals may I display on my PUE?

As many as your meters support, and not one more. With a main meter at 3 % and IT counted at 5 %, a PUE of 1.6 sits between 1.5 and 1.7: displaying 1.58 suggests a precision that does not exist, and rules out any serious comparison with another site.

Is 380 V direct current a good idea for a small company?

No, at that scale. The gain is real — three conversion stages instead of six — but the equipment is less common, the skills rarer and the spares less standard. Below a few hundred kilowatts, AC remains the reasonable choice.

Which suppliers should I contact, and for which item?

Twelve trades are involved: rack distributor, qualified electrician, generator manufacturer, UPS supplier, transfer switch supplier, cooling installer, fire installer, access control installer, cable tray contractor, structured cabling contractor, fibre carrier and electricity supplier. Our tool names the market players for each — and above all what to ask them for in the quote.

Does this guide conclude that you should build?

No, and that is deliberate. Below five racks the fixed items — fire, security, UPS, cooling — do not divide and crush the budget. Our tool costs colocation alongside, and it does sometimes conclude you should not build.

Written on 17 September 2026.

From reading to comparing: relevant data centers

Telehouse - Paris 2 (Voltaire - Léon Frot)
Paris · 356 networks on site · certified ISO 27001, PCI DSS
See the exact price →
Equinix PA2 - Paris, Saint-Denis
Paris · 146 networks on site · certified HDS, ISO 22301
View the listing →
Equinix PA3 - Paris, Saint-Denis
Paris · 122 networks on site · certified HDS, ISO 22301
View the listing →
UltraEdge Lyon-Venissieux
Vénissieux · 83 networks on site · certified ISO 27001, ISO 50001
View the listing →

Estimate my cost →   Compare data centers

Other guides

Guides · Expert answers →

Advertisement